This assignment consists of two parts, with the first part concentrating on identifying risks, issues, assumptions

This assignment consists of two parts, with the first part concentrating on identifying risks, issues, assumptions, and dependencies. Creation of this initial document is a core responsibility of the project manager role. The second part of this assignment is the creation the critical document known as the resource plan. With the knowledge gained from the creation of these two documents, projects are better prepared to course correct when changes occur.

Make a RAID log in an Excel Spreadsheet with clear explanations as to why the individual items are identified and included. Use the project proposal schedule given below to identify potential risks that could occur in the process of executing and implementing the project. Log all assumptions made during the project proposal outline creation for the outline to be feasible. Log all issues that will need to be addressed before the project kickoff. Document all dependencies that impact the project completion. For all dependencies in the RAID log, identify relationships between logged items (i.e., successor and predecessor), as well as if these dependencies are internal to the project and the team or external.

Submit your assignment using the following Excel spreadsheet format:

Sheet 1: RAID Log

———————————————————————————–

Proposal Schedule:

● March 8, 2021 – March 12, 2021 – Procure Assets

Procure Shipping, Insurance, Colocation Service Level Agreements, and Order contingency servers to the new site.

● March 15, 2021 – March 26, 2021 – Prepare Stakeholders/Cloud Testing.

○ Notify and prepare stakeholders for the move.

○ Week of March 15th prepare & train IT staff for teardown of old data center and setup at new location.

○ Week of March 22 prepare non IT stakeholders for downtime.

○ Test cloud backup by creating and restoring small backups in a virtual environment.

● March 27, 2021 – March 28, 2021 – Loading

○ Backup datacenter to secure cloud.

○ Teardown and load data center into trucks.

● March 29, 2021 – April 1, 2021 – Shipping

○ Shipping should take 3 to 4 Business Days.

● April 2, 2021 – April 3, 2021 – Setup

○ Setup and configure data center at new site.

○ Configure Power

○ Configure Network

○ Test systems to ensure proper uptime.

Budget

Item Cost Reason

● Transpak Shipping for 400 servers $50,000 Ship 400 servers from Phoenix to Eastgate Datacenter in Bellevue Washington.

● Transpak Shipping Insurance $100,000 Transpak will insure against damage.

● Eastgate Colocation Cost for 800 $160,000 Each server should take up about 2U of space

U rack space at $200/U First month

● Power First Month $24,480 With an average server using 850 watts/hr (Maddox). 1kWh cost 10 cents in

Washington State.

● Internet first month $400 Calculated with space to grow at $0.2/mb

● Replacement Hardware $60,000 Purchasing 40 extra servers as contingency in case of damage while moving.

● Contingency Budget $131,000 Contingency budget of ⅓ original budget. Us in case of the unforeseen.

● Cloud Backup $10,000 Backup data to cloud before move.

Total

$535,888

Complete Answer:

Get Instant Help in Homework Asap
Get Instant Help in Homework Asap
Calculate your paper price
Pages (550 words)
Approximate price: -
Open chat
1
Hello 👋
Thank you for choosing our assignment help service!
How can I help you?